Scope of Work
What We Did
The work ran in four phases, from documenting the existing layout through final striping.
01
Survey & Demolition
- Note layout of all parking and storage units
- Demo all existing storage units
- Demo existing ceiling grid and tiles
02
Ceiling & Structure
- Clean form deck ceiling to receive rust reversal treatment
- Spray rust reversal treatment to all steel form deck, joists and beams
- Install spray foam insulation to all ceilings
- Install new ceiling tile grid and tiles
03
Leak Repair & Finishes
- Perform grout injections to all walls of garage to stop active leaks
- Prime and paint garage with two tone color scheme
- Restripe parking lines and numbers
04
Storage & Accessibility
- Rebuild new storage units
- Paint storage units with two tone color scheme and number them accordingly
- Demo existing handicap ramp, form and repour concrete to achieve a more gradual slope
- Coat handicap ramp and landing